Location
Tai Po
Client
Water Supplies Department
Construction Period
Aug 2013 – Apr 2016
Contract Sum
$75M
Scope
a) Laying of pipelines:
– Approximately 540m of DN1400 steel pipe
– Approximately 630m of DN1200 steel pipe
– Approximately 50m of DN900 steel pipe
b) Retaining wall of approximately 265m long; and
c) All associated works